Legal Alert |
Texas Dropped the Interconnection Fee. It Did Not Drop the Collateral.
By Paul Turner | Principal, Turner Commodities Law, PLLC
Read the October 9, 2026 update →
PUCT Project No. 58481 · 16 TAC § 25.194 · effective October 8, 2026
The Public Utility Commission of Texas adopted new large-load interconnection standards on September 18. The rule, 16 TAC § 25.194, takes effect October 8, 2026. It implements Senate Bill 6 and PURA § 37.0561. It does not close ERCOT to data centers. It changes who posts money, how much, and how long that money stays posted.
The headline concession is real. The Commission killed the proposed non-refundable interconnection fee and flattened the study fee at a flat $100,000 for every large load. The March proposal's tiered $100,000 / $300,000 split is gone. What remains is more important.
Two security posts, not one
Before a project can enter an ERCOT interconnection study, the customer executes an intermediate agreement and posts $50,000 per megawatt of requested peak demand with the interconnecting distribution or transmission service provider — the DSP or TSP, not ERCOT. That is collateral, not a fee. It is the price of a queue position.
When the Standard Large Load Interconnection Agreement is signed, security is reset to the greater of that same $50,000 per MW of contracted peak demand or the customer's allocated system-upgrade costs. Direct interconnection costs are still paid as contribution in aid of construction. The $50,000-per-MW figure is a floor, not a budget.
Treat it as a floor. A 200 MW project is $10 million on the per-megawatt test. If the study assigns $18 million of upgrades to the customer, the security number is $18 million. If contracted demand grows later, the number can move again.
The study fee is separate
The study fee is a flat $100,000. It is paid to the interconnecting utility at intermediate-agreement execution. The utility remits ERCOT's share on the customer's behalf. It is not refundable. It is a bill for study work, not security. The $50,000-per-MW figure is never a study fee.
Who holds the money
Both security posts go to the interconnecting utility — the DSP or TSP that is actually connecting the load. ERCOT receives only its share of the $100,000 study fee. The collateral sits with the utility as protection against stranded transmission or distribution investment. If a project withdraws after capacity is allocated, the utility draws the security for outstanding amounts and applies the balance under the rule's refund mechanics.
Accepted forms of security
The rule permits three forms: cash collateral, a parental guaranty, or a letter of credit, each subject to the utility's credit-rating thresholds. The rule itself says nothing about segregation, escrow, or separate accounts. A financing-community comment asked the Commission to set firm escrow rules — account structure, what costs can be drawn, refund timelines, and interest on deposits held past a set period. The Commission did not adopt it. Cash collateral sitting in a utility's general accounts is exposed if that utility enters bankruptcy. A letter of credit or parental guaranty is not.
Batch Zero is not a grandfather
The rule reaches covered large-load customers that have not energized by October 8. An existing study position, an intermediate agreement, or a Batch Zero classification does not, by itself, take the project out. Unenergized projects should assume they are in.
First energization is not a full release
Collateral comes back on the milestones in the interconnection agreement — energization, minimum billing demand, construction progress, load ramp, or some mix. A campus can have tenants in a building and still have most of its security sitting with the utility. Phased projects that accept a single project-wide milestone will feel that first. The final rule did soften one operations point: the unused-capacity notice clock now runs 24 months against the energization schedule as a whole, not each milestone. That helps. It does not fix a bad release schedule.
The order also attaches consequences to withdrawing requested or contracted peak demand and to false or inaccurate disclosures. Those will show up in utility default rights and, soon after, in lender and offtaker reps. Previously posted intermediate or Batch Zero collateral may or may not credit toward the SLLIA — ask in writing, and check whether the form still works.
A separate track at 25 MW
Do not mix this rule with the Governor-directed ERCOT audit. Section 25.194 is the interconnection-and-security rule. ERCOT is separately reviewing data centers and crypto facilities at or above 25 MW that have not yet energized — ownership, public incentives, grid versus onsite power, water, cooling, community impact. TCEQ has paused related environmental permits while that work proceeds. A project that stayed under the old 75 MW review line can still land in the 25 MW process as buildings or IT load are added. Keep interconnection filings, ERCOT submissions, financing books, and local-government representations consistent.
What to do before October 8
Confirm whether the load is covered and whether it will be energized before the effective date. Price both security tests, plus CIAC and the flat $100,000 study fee, and stress the case in which allocated upgrades exceed $50,000 per MW. Map every dollar already posted and ask what will be credited. Align SLLIA milestones with actual construction and leasing. Open the power-supply agreement, lease, credit agreement, and EPC for collateral, delay, partial-load, and change-in-demand risk. If the project is a data center or crypto facility at or above 25 MW and is not yet energized, treat the ERCOT information request and the TCEQ pause as live workstreams.
None of this is a ban. It is a change in the cost of a queue position. The questions that matter before October 8 are narrow: Is the load covered? Has it energized? What has already been posted, and will it credit? Does the security number follow upgrades or the per-megawatt test? Do the commercial documents still match the new collateral and delay risk?
Paul B. Turner advises energy clients on ERCOT and PUCT matters. Legal services are provided through Turner Commodities Law, PLLC. This article is commentary, not legal advice.